Happening now on site

Purple Phase

This is the first phase of residential housing. A medium rise development incorporating Murray Green, the property mix includes 10 three-storey houses and 82 one to three bed apartments available for social and market rent.

Current activity:

  • Internal fit out of apartments including kitchens and bathrooms
  • Removal of scaffolding
  • External works and landscaping

See latest site images

Leisure Phase

Use of these new facilities, which include a five court sports hall, 25m swimming pool, 13m learner pool, fitness suite and two multi-purpose studios, will be shared between the school, local sports clubs and the community.

Current activity:

  • Exterior finish
  • Internal fit out of sports hall, studios and fitness suites
  • Tiling of changing rooms and pools
  • Construction of the grandstand overlooking 3G pitch

See latest site images