An individual inspection timeframe will issued for most projects with general inspection stages as follows:
Stage | Contact type | Period of notice required |
---|---|---|
Commencement of work | Email or phone | One day before the works start |
Excavations for foundations | Email or phone | One day before the inspection |
Foundation concrete | Email or phone | One day before the inspection |
Oversite preparation before concreting | Email or phone | One day before the inspection |
Reinforcement before concreting | Email or phone | One day before the inspection |
Damp proof course laid | Email or phone | One day before the inspection |
Exposed drains ready for inspection (and on test) | Email or phone | One day before the inspection |
First floor joists | Email or phone | One day before the inspection |
Steel beams or columns (before encasing) | Email or phone | One day before the inspection |
Roof timbers (before covering) | Email or phone | One day before the inspection |
Completion of works | Email or phone | Within seven days |