Leader update: Victoria Way (A320) closure

Date: 

Friday, 21 February, 2025

An update from Cllr Ann-Marie Barker, Leader of Woking Borough Council, on Victoria Way (A320) closure

“I’d like to begin with the Victoria Arch and Goldsworth Road closures which are adding to Woking’s traffic chaos. The closure is due to a water mains leak affecting the gas network. Both Southern Gas Networks and Affinity Water are on-site to resolve this major issue, which has impacted over 350 local residents. The work is likely to continue into next week.

“Sir Robert McAlpine (SRM) has continued to make steady progress this week, completing the installation of temporary fixings to all ‘high risk’ panels. This is thanks to the arrival of a large crane (known as a Bronto) on site, providing engineers with the safest and quickest means of installing fixings.

“Weather conditions have also remained favourable, allowing engineers to work seven days a week and expedite the work required.

“SRM has appointed a team of independent industry leading façade design specialists that are reviewing why this cladding has failed and whether there is a bespoke solution. I hope to bring you updates on these early discussions as investigations continue.

“Next week, SRM will continue to prioritise other areas of cladding that need to be fixed to allow the safe reopening of Victoria Way (A320) at the earliest opportunity.

“In other news, the back entrance of Marks and Spencer’s has reopened, making it easier for shoppers from the other side of town and residents of the Marches to visit the shop.

“As half term draws to a close, it is likely that congestion on the diversion route will increase next week during rush hour periods. Whilst I appreciate how frustrating this is, your safety remains our priority, and all stakeholders are focused on re-opening the road.

“Also next week, I will be visiting the site to speak to senior SRM staff and get a first-hand understanding of the issues and possible solutions. I know you’ll join me wanting to hear more about the plans to develop a robust, permanent solution to resolve the cladding issue once and for all.

“Whilst disruption continues, I encourage you to read the frequently asked questions and answers if you have any queries.

“Thank you for your continued patience.”

Thank you. 
Cllr Ann-Marie Barker.